Efficient assembly of urban systems: a look behind the scenes

The assembly of urban systems, such as enclosures and shelters, is a well-structured process. At projekt w, we rely on precise planning, careful preparation and professional implementation to ensure that every project is a success. Find out how we take projects from the initial idea to completion.

solarpw1112204 1864 1

1. Planning and time frame

The time between the first draft and installation is usually 12 weeks. This period ensures that all steps – from commercial and technical clarification to site preparation – are properly coordinated.


2. Site preparation: What needs to be done?

A well-prepared site is the key to a smooth installation. The following requirements must be met:

  • Foundations: These should be constructed according to the calculated static requirements.
  • Storage area: Provision of a suitable area for components and assembly aids.
  • Access: Free access to the place of use.

For safety reasons, we carry out a preliminary inspection in advance.

In doing so, we document the delivery situation, any special features and clarify any open questions with you.

To ensure that everything is ready, we carry out a site inspection in advance. During this inspection, we create a detailed protocol in which the delivery situation, contact persons and possible deviations are documented.


3. How customers can save time and money

Correct implementation of the foundations reduces unnecessary delays and costs.

We support you with detailed plans and are currently developing a handout for smaller construction projects that will make it easier for you to prepare independently. Our team is at your side.


4. Professional installation

Our three experienced installation teams ensure a quick and smooth implementation. Depending on the size of the project, installation is usually completed within 1–2 working days.


5. Flexible anchoring

Our supports offer two options for anchoring:

  • concrete embedding for particularly robust anchoring
  • and bolting for flexible and faster implementation

Both variants guarantee a stable construction, customised to your needs.


6. Flexibility in anchoring

Our supports offer two options for anchoring:

  • concreting for particularly robust anchoring
  • dollying for flexible and faster implementation

6. Photovoltaic systems: single-source integration

Projects with PV systems are realised in collaboration with our partner Reyting GmbH:

  • Delivery of the PV modules and substructure directly to the construction site.
  • Installation of the modules by our teams, based on a detailed layout plan.
  • The DC-side work includes the connection of the PV modules to each other and the laying of the strings to the cable laying on the support; all further steps are carried out on site.

7. Green roofs: care from the outset

Our fitters will fertilise the greening on enclosures with green roofs when they carry out the initial installation. We provide care instructions for further maintenance, which can be easily downloaded from our homepage.


8. Challenges and solutions

Unforeseen problems can always arise. In such cases, our experienced contacts – Ms Vogt, Mr Arens and Mr Bertling – are on hand to provide quick and pragmatic solutions.


9. Installation in sensitive locations

In areas such as city centres or industrial plants, special challenges can arise, particularly with regard to delivery. In some cases, a truck-mounted crane is required to bring the components safely to their destination.


10. Acceptance and commissioning

After installation is complete, the customer carries out the acceptance. This involves checking whether the work has been carried out in accordance with the contract and without visible defects.

As a rule, the paving is completed on site and profile cylinders are installed before commissioning.


With our structured approach, experienced installation teams and close collaboration with you, we ensure that each project is implemented efficiently and to a high standard.

Do you have any questions or are you planning a project? We look forward to supporting you!

Visit us at www.projekt-w.de

image060
image064 1
image001